Skip to content
DCIM ProfessionalsDCIM Professionals

Power & UPS Tool

Battery Backup Estimator

Size a battery bank for any critical load. Build a load list from individual devices, set target runtime and DC bus voltage, apply depth-of-discharge, temperature and aging derating, then calculate required Ah capacity and battery count. Export the full load list as CSV or Excel.

June 2026Battery backup reference

Quick Answer

Required Ah = (Load W × Runtime h) ÷ (DC voltage × Efficiency × DOD × Derating).

A 3 kW load needing 1 h backup on a 48 V bus at 90 % inverter efficiency, 80 % DOD and 85 % combined derating needs ≈ 103 Ah at the battery terminals — typically 2 × 12 V 55 Ah AGM batteries in parallel (4 in series). Always verify with the battery datasheet and include a safety margin.

System Configuration

Battery backup system sizing

Configure the DC bus voltage, battery type and derating factors. Add individual loads below or enter the total load directly. Set your target runtime to calculate the required battery bank.

Load from list0 W

Quick presets — common backup scenarios

Load list

Load List

Loads on this battery bank — saved in browser

Each load group contributes to the total power the battery bank must sustain during backup.

IDDescriptionWattsQtyTotal WNotes
No loads added yet. Use presets or the form above, or enter total load in the override field.

Method

How the battery sizing is calculated

Energy required (Wh) = Load (W) × Runtime (h) ÷ Inverter efficiency. Required Ah at the DC bus = Energy (Wh) ÷ DC voltage ÷ (DOD × Temperature derating × Aging factor).

Ah = (W × h) ÷ (V × η_inv × DOD × f_temp × f_age)

Batteries in series = DC bus voltage ÷ battery nominal voltage (rounded up to nearest integer). Strings in parallel = Required Ah ÷ battery rated Ah (rounded up). Total batteries = series × parallel.

DOD

Why depth of discharge matters

Lead-acid (VRLA/AGM/Gel) batteries suffer accelerated wear below 50 % DOD. Cycling below 80 % DOD more than occasionally can halve cycle life. LiFePO₄ chemistry tolerates 80–90 % DOD routinely. Setting a conservative DOD means you size for more Ah up front but protect battery life.

Temperature

Temperature derating for lead-acid

Lead-acid battery capacity drops roughly 1 % per °C below 25 °C. At 0 °C a battery rated 100 Ah delivers around 75 Ah. LiFePO₄ is more stable but still derate 5–15 % below 10 °C. Always check the manufacturer datasheet for the actual capacity-vs-temperature curve.

FAQ

Battery backup sizing questions

What DOD should I use for VRLA/AGM batteries?

50 % DOD is the standard long-life design point for lead-acid in standby/UPS applications. This maximises cycle count — typically 200–500 full cycles to 50 % DOD. For occasional emergency backup where batteries rarely discharge, 80 % DOD is acceptable. Never design for 100 % DOD; you will damage the cells and void the warranty.

Should I include a safety margin on top of the calculation?

Yes — add 20–25 % margin beyond the calculated Ah requirement. This accounts for load growth, actual vs rated capacity variation between battery units, battery replacement scheduling and worst-case temperature or aging coincidence. It is also common to round up to the next standard battery string configuration.

What is the aging factor and when does it apply?

Battery capacity degrades over time — lead-acid typically to 80 % of rated capacity after 3–5 years, and IEEE 485 defines end-of-life as 80 % of original capacity. An aging factor of 80 % means you size the bank to deliver the required runtime even at end-of-life, so the bank will be oversized when new. This is good practice for mission-critical installations.

How do I choose the DC bus voltage?

Common DC bus voltages: 12 V and 24 V for small consumer UPS systems. 48 V is the standard for telecom, small data centre UPS and modern home energy systems — lower current for the same power, smaller cable cross-section. 120 V DC is used in utility and large industrial UPS systems (IEEE 485). 240 V DC in large data centre UPS (matching the rectifier bus).

Can I mix different battery capacities or ages in the same string?

Never mix batteries of different Ah ratings in the same parallel string — weaker cells will be overloaded during charging and discharge. Mixing old and new batteries in the same bank causes premature failure of the new cells. Replace battery strings as a complete set or full bank.

Project

Need help with UPS or battery bank design?

ITCOREOPS supports UPS sizing, battery bank design, critical power infrastructure documentation and data centre power resilience planning.

Disclaimer

Planning estimate only

This estimator produces a planning-level result. It does not replace a site-specific load study, battery datasheet analysis, charger sizing, IEEE 485 / EN 50272-2 compliance check, or review by a qualified electrical engineer.

Workflow

Build your load list before sizing the battery bank.

Add every protected load, set the target runtime and DC bus voltage, apply real derating factors, then export the full sizing summary for procurement and commissioning documentation.

Enter exact inputs above ↑

Support

Need help with battery backup or UPS design?

For critical power infrastructure, UPS sizing, battery bank specification and data centre resilience, visit ITCOREOPS.

Feedback

Missing a battery type or derating option?

Report display issues, missing battery chemistries, incorrect default values, or feature requests for this estimator.